How to Fill Out an F10 Notification Form (CDM Regulations)

If you’re planning a construction project in the UK, you may need to submit an F10 notification form to the Health and Safety Executive (HSE). This is a legal requirement under the Construction (Design and Management) Regulations 2015 (CDM 2015), and failing to do so could result in enforcement action.

In this guide, we’ll walk you through what the F10 form is, when it’s required, and how to fill it in correctly—so your project stays compliant from day one.

What Is an F10 Notification?

Under CDM 2015, notifiable construction projects must be reported to the HSE before work begins. This is done using the F10 form, which notifies the HSE of key project information and ensures that health and safety are properly managed on site.

“The client must give notice in writing to the Executive as soon as is practicable before the construction phase begins.”
— HSE, CDM Regulation 6

When Is an F10 Form Required?

You must notify the HSE via an F10 form if your project:

  • Will last longer than 30 working days and have more than 20 workers working simultaneously at any point, OR
  • Will exceed 500 person-days of construction work.

If either condition applies, you’re legally required to complete and submit an F10.

How to Complete the F10 Form – Step by Step

You can submit the F10 online directly through the HSE portal. Here’s what you need to prepare:

  • Step 1: Client Details
    Provide the name, address, telephone number, and email of the client (domestic or commercial).
  • Step 2: Principal Designer & Principal Contractor
    List the Principal Designer and Principal Contractor, including their contact details. These roles are key to ensuring CDM compliance.
  • Step 3: Project Details
    Add the site address, description of the project, estimated start and end dates, and the number of expected workers.
  • Step 4: Notification
    Confirm whether the project involves more than one contractor and that the required appointments have been made.
  • Step 5: Submit the Form
    Once complete, submit it online. You’ll receive a project reference number and an electronic copy of the notification for your records.
“The F10 should be clearly displayed in the construction site office and kept up to date if the project details change.”
— HSE Guidance, CDM FAQs

Useful Links

Final Thoughts: Stay CDM Compliant

Completing and submitting an F10 form is a critical step in any notifiable construction project under CDM 2015. It ensures accountability, proper planning, and a safe working environment from the very beginning.

Need help with CDM compliance, principal designer responsibilities, or project safety planning? Explore our health and safety training courses or contact us at sales@pglmidlands.com for expert advice and guidance.